Neighbors,
Here is a link to the full recording of the People’s Gas town hall regarding the installation of new gas main on Rockwell, Argyle, Ainslie, and Winnemac:
https://us02web.zoom.us/rec/share/95R5MpWv93hOGYWQx3nBUa8iHJ7Aaaa82nBK_ftbnR3jTLnYzME8N6DbM1fbQQM
Meeting summary:
- main installation complete on Rockwell — work will shift to Winnemac, then Argyle, and then Ainslie
- roughly one week for main installation per street (slightly longer on Ainslie due to length)
- after main installations, crew will circle back to Rockwell to begin service transfers, then Winnemac, then Argyle, and then Ainslie
- schedule for connecting meters (requires access to homes) TBD, based on COVID-19 guidelines from the state and city