Status: In progress

Ravenswood Avenue Arterial Resurfacing

Project type: Arterial, Collector Resurfacing, Streets

Project Summary

Intersection of Ravenswood Avenue with cyclist
Intersection of Ravenswood Avenue. Photo credit: John Greenfield, Streetsblog Chicago

Ravenswood Avenue from Wilson Avenue to Peterson Avenue will be undergoing an arterial resurfacing project, beginning in May 2025!

Project Overview

  • Neighborhood: West Edgewater, West Andersonville, Ravenswood
  • Zip Code: 60640, 60660
  • Scope and boundaries: Ravenswood Avenue from Wilson Avenue to Peterson Avenue
  • Timeline: Spring-Summer 2025

Status: In progress

Ravenswood Avenue

Ravenswood Avenue will be completely resurfaced from Wilson Avenue to Peterson Avenue. As part of Chicago’s Complete Streets Ordinance, any arterial resurfacing project must also include pedestrian and bike safety infrastructure, including curb and sidewalk improvements and safer pedestrian crossings.

The resurfacing projects will include both concrete work as part of the pedestrian infrastructure improvements, and asphalt resurfacing.

Asphalt resurfacing is usually done in several blocks at a time. The existing asphalt is first milled; 2-3 weeks later, the 1st layer of asphalt is laid, and 2-3 weeks after that, the 2nd and final layer of asphalt is laid. Arterial resurfacing projects do not generally require full road closures, but instead lane closures as needed.

Rendering of bumpouts and bike-friendly speed humps

Project Features

  • Pavement resurfacing
  • Curb extensions/bumpouts
  • New sidewalk and curb and gutter improvements
  • New crosswalks
  • Bike corrals

Project Timeline

  • Bidding: Fall 2024
  • Construction Start: May 2025
  • Estimated Completion: August 2025

Construction Updates

Construction is tentatively scheduled to begin on May 22, 2025, pending weather and clearance from and coordination with existing utilities! Contractors will begin working on the north side of the project. All work on this corridor is scheduled to be completed by the end of August.

See weekly updates below!

Community Engagement

Subscribe to our newsletter for regular updates on the Ravenswood Avenue resurfacing project!

Archived Meetings

Subscribe to Updates

Name(Required)
Street Address
Subscribe me to the following 40th Ward emails:
This field is for validation purposes and should be left unchanged.