Status: Upcoming

Western Avenue Arterial Resurfacing

Project type: Arterial, Collector Resurfacing, Streets

Project Summary

Intersection of Western and Winnemac
Intersection of Western and Winnemac

Western Avenue from Foster Avenue to Leland Avenue will be undergoing an arterial resurfacing project starting in Summer 2024.

Project Overview

  • Neighborhood: Lincoln Square, Budlong Woods
  • Zip Code: 60625
  • Scope and boundaries: Western Avenue from Foster to Leland
  • Timeline: Summer-Fall 2024

Status: Upcoming

Western Avenue Resurfacing

Continuing the Western Avenue resurfacing project north of Foster that was completed in 2023, Western Avenue will be repaved from Foster to Leland this year, which will connect it to the Western Avenue Brown Line improvement project.

As part of Chicago’s Complete Streets Ordinance, any arterial resurfacing project must also include pedestrian and bike safety infrastructure, including curb and sidewalk improvements and pedestrian safety improvements like bumpouts and pedestrian islands to create crossings.

The resurfacing project will include both concrete work as part of the pedestrian infrastructure improvements, and asphalt resurfacing.

Asphalt resurfacing is usually done in several blocks at a time. The existing asphalt is first milled; 2-3 weeks later, the 1st layer of asphalt is laid, and 2-3 weeks after that, the 2nd and final layer of asphalt is laid. Arterial resurfacing projects do not generally require full road closures, but instead lane closures as needed.

Renderings of curb extenstions and pedestrian refuge island

Design Exhibits

  • TBA

Project Features

  • Pavement resurfacing
  • New pedestrian refuge islands
  • Curb extensions/bumpouts
  • Sidewalk ramp and curb improvements

Project Timeline

  • Bidding: Summer-Fall 2024
  • Construction Begins: August 2024
  • Estimated Completion: Fall 2024

Construction Updates

Latest Update as of 7/8/24: As of this week, the Damen Avenue resurfacing from Argyle to Farragut is scheduled to commence in mid-August.

Community Meetings

Subscribe to our newsletter for regular updates on the Western Avenue resurfacing project!

Archived Meetings

  • The Western Avenue resurfacing project was announced at the 40th Ward Infrastructure Town Hall on June 5th. Watch the video presentation (Damen Avenue section begins at 22:58).

Subscribe to Updates

Name(Required)
Street Address
This field is for validation purposes and should be left unchanged.