Project Summary
The new Peterson/Ridge Metra station, the newest addition to Metra’s UP-N line, was completed in May 2024. We’re thrilled to be welcoming a new transit option to the 40th Ward that will better connect our community to downtown and other neighborhoods across the city! The station was originally proposed over a decade ago, and it has taken the collective and dedicated efforts of many city and state legislators to bring it into reality.
Project Overview
- Neighborhood: West Edgewater, West Ridge
- Zip Code: 60660
- Scope and boundaries: 1780 W Peterson Avenue
- Timeline: Completed in May 2024
Status: Completed
Quick Links
Scope & Design
Peterson Ridge Metra Station
Metra completed the Peterson/Ridge station, a new station/stop on the UP-N line at Peterson Avenue, on May 20th, 2024. The station includes an elevated platform and warming house above Peterson Avenue, with entrances on both the north and south sides of the street. A small drop-off and disabled parking circle drive will be installed north of Peterson Avenue, with nose-in parking spaces running along Ravenswood Avenue south of Peterson Avenue.
Project Goals
- Connect transit riders to downtown, city neighborhood, and the suburbs
- Encourage transit-oriented development on some of the nearby side streets and along Clark Street
- Drive more foot traffic to local businesses
Press & Media
- Edgewater Metra Station Opens This Month After Decade Of Planning, Construction, via Block Club Chicago
- Right on time: New Metra station in Edgewater is a good sign for public transit’s future, via the Chicago Sun Times
- New Metra Station In Edgewater Will Help Transform Area, Officials Say: ‘I Am Elated’, via Block Club Chicago
- Metra to break ground on long-planned Peterson Ridge station in Edgewater, via the Chicago Tribune
Design Exhibits
- Overhead Site Plan (PDF)
- Site Plan North Detail (PDF)
- Site Plan South Detail (PDF)
- Station warming house and plaza rendering (PDF)
Project Features
- Two new six-vehicle platforms for travel in both directions but with an emphasis on downtown-bound traffic
- The south-bound platform will include the station building with both sides featuring warming shelters
- 49 vehicle parking spaces, five of which will be ADA compliant, around the facility
- New drop-off and pick-up area with a turnaround for cars with bicycle parking
Timeline & Construction Updates
Project Timeline
- Bidding: Complete
- Construction: Complete
- Estimated Completion: Spring 2024
Construction Updates
To see the latest project updates from the contractor, please click the cards below.
- See Community Meetings.
- The station was completed on May 20th, 2024!
Engagement
Community Meetings
Archived Public Meetings
- March 13, 2024 – Metra Community Meeting, Video Recording
Archived Newsletters
- 10/14/2022 – Peterson/Ridge Metra Project Updates
- 10/12/2022 – Peterson/Ridge Metra Project Updates
- 09/23/2022 – Peterson/Ridge Metra Project Updates
Subscribe to Updates
From the blog
Peterson Ridge Metra Updates
Sorry, no posts to display.